What data will be left for the new pump test operation? A comparable baseline is established
The flow, import and export pressure, speed rotation, current and vibration are recorded under the same conditions.
Clear recording of position before running
The test operation records indicate the location of the equipment number, flow meter and pressure point, as well as the actual configuration, valves, fluid supply level and mode of operation of the pump team.
Record readings after stabilizing the work
The pressure, flow, current, speed, temperature and vibration are recorded under the agreed load, and the data are compared to the delivery curve and project requirements. The results of the anomaly, adjustment and re-detection can be presented on the same page, and the baseline can be placed in the equipment archive.